The Manali-Leh highway was built by the Border Roads Organisation (BRO), which began work from both ends in 1964. By 1989 a 473 km road was serving as the second land route into Ladakh after the Srinagar-Leh road. The Atal Tunnel under Rohtang, opened on 3 October 2020, shortened the Himachal side by about 45 km, and today the highway (part of NH 3) is about 428 km long.
- 1964: BRO started the road from both ends at once.
- 1989: a 473 km road became Ladakh's second land route, after Srinagar-Leh.
- 3 Oct 2020: Atal Tunnel cut about 45 km and replaced Rohtang La on the main line.
- Four passes above 4,700 m still close the road from about November to May.
- 42 days: the 2026 snow clearance, ending in the Golden Handshake at Sarchu on 12 May.
It is still a seasonal road. Every spring BRO's Project Deepak digs north from Manali and Project Himank digs south from Leh until the two meet at Sarchu. In 2026 that took 42 days, from 27 March to 12 May.
This post walks through the road's history in dates, explains why the high passes still close for half the year, and shows what changes when the next tunnel, Shinku La, opens.
When was the Manali-Leh highway built?
Construction began in 1964, with BRO crews working from the Manali end and the Leh end at the same time. Before the road, these passes were crossed on foot and with pack animals, and Ladakh's only road link was the Srinagar-Leh route over Zoji La, which India had fought to hold in 1948.
Long before the BRO, the Manali side was a caravan route. In mid-May 1820, William Moorcroft, an English explorer working for the East India Company, finally won Maharaja Ranjit Singh's permission to travel through Sikh territory, and in August he joined his companion George Trebeck and their caravan at Sultanpur in the Kullu valley. They followed the Beas up to the Rohtang Pass, at 13,300 ft (4,100 m), came down into the Lahul valley and went on to Leh, arriving on 24 September 1820.
Moorcroft had come for Turkoman horses and to gather intelligence for the Company. He spent nearly two years in Ladakh waiting for Chinese permission to go on to Yarkand, and signed a trade treaty with the Ladakhi government that the Company repudiated. He reached Kashmir only on 3 November 1822. Riders now cover the ground from Kullu over Rohtang into Lahul and on to Leh in about two days.
Wikipedia: William Moorcroft (explorer), citing Meyer and Brysac, Tournament of Shadows (1999)A quarter of a century to build
The Manali route took a quarter of a century. By 1989 a 473 km road was in use as the second land approach to Ladakh. That date matters for two reasons:
- A second military route. It gave the Army a second route into Ladakh, so a single blocked pass on the Srinagar side no longer cut the region off.
- A new door for civilians. It opened Ladakh to travellers from Himachal Pradesh, and over the next three decades it became the classic Indian motorcycle trip.
Who looks after the road
The road has always been a BRO road. BRO designed it, built it and still maintains it, through projects that split the work at the Himachal-Ladakh border:
- Project Deepak looks after Manali to Sarchu.
- Project Himank looks after Sarchu to Leh.
- Project Yojak, set up in 2022, handles tunnels and roads on the Manali-Ladakh axis.
My history of the Border Roads Organisation explains how these projects fit into BRO's wider map.
| Year | Event |
|---|---|
| 1964 | BRO starts building the Manali-Leh road from both ends |
| 1976 | BRO completes the Khardung La road north of Leh, extending the Himank network |
| 1989 | A 473 km Manali-Leh road serves as Ladakh's second land approach |
| 3 Jun 2000 | Prime Minister Atal Bihari Vajpayee announces a tunnel under Rohtang |
| 26 May 2002 | BRO is given charge of the Rohtang tunnel project |
| 28 Jun 2010 | Drilling starts at the south portal |
| 13 Oct 2017 | The two tunnel faces meet |
| 25 Dec 2019 | Rohtang tunnel renamed Atal Tunnel |
| 3 Oct 2020 | Atal Tunnel inaugurated; the Himachal section shrinks by about 45 km |
| 2022 | Project Yojak raised for tunnels and roads on the Manali-Ladakh axis |
| 23 Apr 2024 | BRO connects the highway end to end, an early year |
| 13 May 2025 | BRO connects the highway for the 2025 season |
| 20 Nov 2025 | Route beyond Zingzingbar closed for winter |
| 12 May 2026 | Golden Handshake at Sarchu after 42 days of snow clearance |

Which passes does the Manali-Leh highway cross, and how high are they?
Before the Atal Tunnel, the road crossed five high passes. The tunnel removed Rohtang from the main line, so a rider now crosses four, with Tanglang La the highest at 5,328 m (17,480 ft).
- Rohtang La, 3,980 m: now off the main line, bypassed by the tunnel.
- Baralacha La, about 4,850 to 4,890 m: the first high pass after the tunnel.
- Nakee La, 4,739 m: above the Gata Loops.
- Lachulung La, 5,065 m.
- Tanglang La, 5,328 m: the highest point, between Pang and Upshi.
Sarchu, at 4,200 m, marks the Himachal-Ladakh border and the halfway camp.
See the data as a table
| Altitude (m) | |
|---|---|
| Atal Tunnel (north portal area) | 3071 |
| Rohtang La (old route) | 3980 |
| Baralacha La | 4850 |
| Sarchu | 4200 |
| Gata Loops top | 4190 |
| Nakee La | 4739 |
| Lachulung La | 5065 |
| Tanglang La | 5328 |
Source: Wikipedia: Leh-Manali Highway; Jain and Varma (2025) for the tunnel · Gata Loops: 21 hairpin bends climbing about 500 m. Tanglang La is given as 5,328 m in the route table and 5,359 m in another listing.
The altitude explains the season. Everything above about 4,500 m gets several metres of snow from November, and the Manali-Sarchu stretch alone has 26 avalanche-prone points according to BRO. Snow does not just sit on the road; it slides onto it again after it has been cleared.
That is why the opening date moves every year, and why the most reliable advice for riders is to aim for mid-June to September. The Leh-Ladakh bike trip guide covers the full route planning, and you should build in the acclimatisation plan because the road climbs past 5,000 m within two riding days of Manali.

How did the Atal Tunnel change the Manali-Leh highway?
The 9.02 km Atal Tunnel under the Pir Panjal range replaced the Rohtang crossing, cutting Manali to Keylong from about 116 km to 71 km and the drive from 5 to 6 hours to about 2. It sits at roughly 3,000 to 3,071 m, nearly 1,000 m below Rohtang La, which is why Lahaul now stays connected to Manali for most of the winter.
It was an expensive, slow, difficult tunnel. The 2000 estimate was ₹500 crore; the final cost was about ₹3,200 to 3,300 crore, depending on the source.
| Atal Tunnel problem | When | What happened |
|---|---|---|
| Water ingress | June 2012 | Up to 30 lakh litres of water a day entering the tunnel |
| Roof collapse | 17 October 2013 | About 30 m of roof fell, halting excavation |
| Seri Nala fault zone | Through construction | Crushed, water-bearing rock: the worst stretch |
The authors reviewed geotechnical surveys, construction records and performance data for the 9.02 km tunnel built with the New Austrian Tunnelling Method (NATM). They report up to 1.9 km of rock above the tunnel and rock mass ratings of only 21 to 40 (poor rock), which forced an adaptive support design. The tunnel is a single horseshoe tube with an 8 m roadway, 5.525 m headroom and an emergency escape tunnel built under the road deck. Cost rose from ₹500 crore to about ₹3,300 crore, and travel time fell by 4 to 5 hours. The limit: this is a review based on published records, not new field measurements, so treat its numbers as a summary of BRO's data rather than an independent check.
Read the paper (free)
For riders the change is bigger than the distance saved. Rohtang used to be the first and worst test of the trip, a muddy, crowded pass at almost 4,000 m that many people crossed on their first morning out of Manali.
Now the first high pass is Baralacha La, and the climb to altitude is more abrupt: you exit the tunnel into Lahaul, reach Keylong, and can be at 4,850 m or higher the same day.
That makes acclimatisation a bigger issue than it was when Rohtang slowed everyone down. My piece on how Himalayan tunnels are changing road trips looks at this effect across Atal, Sela and Zojila.
Why does the highway still close every winter?
The tunnel solved Rohtang, but four passes above 4,700 m remain. Baralacha La alone sits at about 4,850 to 4,890 m (BRO gives 16,040 ft). From roughly November to April these passes are under snow, and the road is officially closed beyond the Lahaul villages. In 2025 Lahaul-Spiti police closed the route beyond Zingzingbar on 20 November on BRO's advice.
Snow is only part of the problem. Freeze and thaw break the rock itself:
- Water gets in. Melt and rain seep into cracks in the rock in summer.
- It freezes. In winter the water turns to ice and expands.
- Blocks are wedged loose. Each cycle opens the crack a little more until a block falls.
That is why the road shows fresh rockfall every spring, even on stretches that saw no avalanche.
Researchers from IIT (ISM) Dhanbad, IIT (BHU) and IIT Bombay sampled rock from a slope on the Manali highway between Solang and the Rohtang tunnel's south portal. They put specimens through repeated freeze-thaw cycles in the lab, measured strength, and built a 3D model of the slope in 3DEC. Compressive and tensile strength fell as the number of cycles rose, and in the model the blocks moved further and the slope's factor of safety dropped. The limit: this is a conference abstract, and it does not publish the number of cycles or the percentage strength loss. The direction of the result is still the useful part: every winter weakens the slopes above the road.
Read the abstract (free)What is the Sarchu "Golden Handshake"?
The Golden Handshake is the moment each spring when the Project Deepak team coming north from Manali and the Project Himank team coming south from Leh meet at Sarchu, which marks the end of snow clearance. In 2026 it happened on 12 May. Officers of both projects met at Sarchu, and the road was handed to the Lahaul-Spiti administration for a joint safety assessment before traffic was allowed.
The 2026 season was hard. The Tribune reported that work started on 27 March and that crews had to pull back and restart at least six times as fresh snow and avalanches undid their work. After the handshake, light vehicles moved on alternate days for about two weeks on the Darcha-Sarchu section, and two-way traffic was allowed from 1 June 2026, according to a route-status tracker that follows the official advisories.
| Season | BRO connects the highway | Notes |
|---|---|---|
| 2024 | 23 April 2024 | An unusually early year |
| 2025 | 13 May 2025 | Tourist traffic from late May; closed beyond Zingzingbar 20 Nov 2025 |
| 2026 | 12 May 2026 | 42 days of clearance from 27 March; two-way traffic from 1 June |

What comes next: Shinku La and the other tunnels
The next big change is the 4.1 km Shinku La tunnel, expected around August 2028. It is not on the Manali-Leh highway itself; it sits on the Nimmu-Padum-Darcha road through Zanskar, which gives a second route from Lahaul to Leh. When it opens, Ladakh will have a third, lower and potentially all-year road from Himachal.
On the main highway, three more tunnels are at planning or detailed project report stage:
- Baralacha La: about 13.7 km.
- Lachung La: about 14.7 km.
- Tanglang La: about 7.32 km.
None has a construction date. If they are ever built, the Manali-Leh highway would stop being a summer-only road, and the ride would lose much of what makes it a test.
A region held by one road is held by one pass. Every tunnel on this highway is an answer to that.
That trade-off, faster supply lines and safer travel for locals against a gentler adventure for tourists, is the real story of this road's next decade.
If you are choosing between this road and the Srinagar side for your first trip, read my comparison of Ladakh via Manali or Srinagar and the companion history of the Srinagar-Leh highway and Zoji La. Other routes I cover are on the Ride Atlas page.
What's new
- BRO reopens the Manali-Leh highway after a 42-day snow clearance, meeting at Sarchu The Tribune, May 2026
- Manali-Leh highway status tracker: two-way traffic from 1 June 2026 Discover with Dheeraj, Oct 2026
- 125 BRO projects, including Himachal and Ladakh works, dedicated in one day Swarajya, Dec 2025
Questions people ask
When did the Manali-Leh highway open to the public?
BRO started building it in 1964, and by 1989 the 473 km road was serving as Ladakh's second land approach. It has carried civilian traffic in summer since then, subject to the annual snow closure.
How long is the Manali-Leh highway now?
About 427 to 428 km, with about 177 km in Himachal Pradesh and 251 km in Ladakh. The Atal Tunnel cut roughly 45 km from the old 473 km route by bypassing Rohtang La.
Is the Manali-Leh highway open all year after the Atal Tunnel?
No. The tunnel keeps Manali connected to Lahaul in winter, but Baralacha La, Nakee La, Lachulung La and Tanglang La still close from about November to May. In 2026 BRO reconnected the road on 12 May.
Which is better for a first Ladakh trip, Manali or Srinagar?
The Srinagar side opens earlier and climbs more gradually, which helps acclimatisation. The Manali side is higher and wilder. Many riders go in from Srinagar and out via Manali for that reason.
What is the highest point on the Manali-Leh highway?
Tanglang La, given as 5,328 m (17,480 ft) in the route table, with some sources listing 5,359 m. It sits between Pang and Upshi on the Ladakh side.
Sources
- Wikipedia: Leh-Manali Highway (accessed 2026)
- Wikipedia: Atal Tunnel (accessed 2026)
- Wikipedia: Border Roads Organisation (Project Yojak, project list) (accessed 2026)
- Wikipedia: Khardung La (road built 1976) (accessed 2026)
- Jain A. and Varma H.: Structural Design and Geotechnical Analysis of the Atal Tunnel, Transportation Development Research (2025)
- Sardana S. et al.: Instability in Himalayan Rock Slope under Recurrent Freeze-Thaw, EGU2020-9058 (2020)
- The Tribune: BRO reopens Manali-Leh National Highway after 42-day clear-up (2026)
- Discover with Dheeraj: Manali Leh Highway status 2026 (2026)
- Tripoto community: Ladakh bike trip route question
- Swarajya: 125 BRO projects worth ₹5,000 crore dedicated to nation (2025)
- Wikipedia: Operation Bison (Battle of Zoji La), citing S. K. Sinha, Operation Rescue (1977) (accessed 2026)
- Wikipedia: William Moorcroft (explorer), citing Meyer and Brysac, Tournament of Shadows (1999) (accessed 2026) (source for the story)