Zoji La history: the Srinagar-Leh road from 1948 to the tunnel

Tanks crossed it in 1948, snow shut it for half the year until about 2020, and on 9 June 2026 the tunnel beneath it broke through. A dated history of Ladakh's oldest road gate.

The dusty hairpin shelves of the Zoji La road cut into a steep Himalayan slope above a green valley in Kashmir
Photo: VinayakPhadatare, CC BY-SA 4.0, via Wikimedia Commons

Zoji La is the pass at about 3,500 m (BRO and the press give 11,500 to 11,650 ft) that carries the Srinagar-Leh highway, NH 1, from the Kashmir Valley into Ladakh. India recaptured it with light tanks on 1 November 1948 in Operation Bison, and for decades it stayed shut for 150 to 180 days each winter. BRO cut that to 32 days by 2025, and the 13.15 km Zojila tunnel beneath it achieved its final breakthrough on 9 June 2026, with completion targeted for February 2028.

Key takeaways
  • 1 November 1948: Operation Bison retook Zoji La with M5 Stuart light tanks, then the highest armour had fought anywhere.
  • 150 days was BRO's typical winter closure; it fell to 73 (2021-22), 68 (2022-23) and 32 days (2024-25).
  • 13 January 2025: the 6.5 km Sonamarg (Z-Morh) tunnel opened, 13 years after approval.
  • 13.153 km Zojila tunnel broke through on 9 June 2026; target February 2028, at ₹6,809 crore estimated.
  • More than 3 hours to about 15 minutes: the crossing time the tunnel is meant to deliver.

No Himalayan pass in India has a denser history per kilometre. Zoji La is about 100 km from Srinagar and 15 km beyond Sonamarg, and it is the only road gate between Kashmir and the Dras and Suru valleys. This post lays out what happened here and when, why the pass closes, how BRO shrank the closure, and what the two tunnels on NH 1 mean for riders.

1 Nov 1948Operation Bison retakes the pass with tanks
32 dayswinter closure in 2025, from about 150
13.15 kmZojila main tunnel, broke through 9 Jun 2026
Feb 2028completion target (Lok Sabha, Jul 2025)

Where is Zoji La and why does it matter?

Zoji La sits on the Great Himalayan range between Ganderbal district in Jammu and Kashmir and Kargil district in Ladakh.

West sideEast side
ValleySind valley, around SonamargDras valley, on to Kargil and the Indus
CharacterGreen and wetDry
AdministrationGanderbal district, J&KKargil district, Ladakh

The pass is short and low by Ladakh standards, but it is the first ridge the western weather systems hit, which is why it gets so much snow. Satellite-based climate data for the pass record lows of about minus 44 °C in December and January.

Whoever holds Zoji La holds the overland route into Ladakh from the west.

That combination of heavy snow and steep, avalanche-prone slopes is why the pass shaped every chapter of the road's history.

The gravel road climbing towards Zoji La with a sheer mountain wall and a steep drop beside it
The climb to Zoji La from the Sonamarg side, a narrow shelf road cut into the slope.Photo: Kondephy, CC BY-SA 3.0, via Wikimedia Commons

What happened at Zoji La in 1948?

In 1948, during the first India-Pakistan war over Kashmir, Gilgit rebels and a Pakistani force under Major Muhammad Khan Jarral seized Zoji La, cutting Ladakh off from the Kashmir Valley.

The story

The Indian Army had already failed once at the pass. Operation Duck, an attack by the 77th Parachute Brigade under Brigadier K. L. Atal, could not shift the raiders. For the second try, renamed Operation Bison by Lt Gen K. M. Cariappa, the army chose something nobody expected at that height: tanks.

The M5 Stuart light tanks of the 7th Light Cavalry were moved through Srinagar dismantled and winched across bridges, while two field companies of the Madras Sappers turned the mule track from Baltal over the pass to Gumri into a jeep track that could carry them. On 1 November 1948 the brigade attacked with armour, backed by two regiments of 25-pounders and a regiment of 3.7-inch guns, and forced the pass. On 24 November it linked up at Kargil with troops advancing from Leh. India lost 75 killed and 296 wounded.

Wikipedia: Operation Bison (1948), with its cited military histories
A preserved M5 Stuart light tank in olive drab with a star and USA lettering on a lawn, seen from the side
An M5 Stuart light tank, a museum example in Indiana, US. Tanks of this type, from the 7th Light Cavalry, were taken apart and winched up to Zoji La in 1948.Photo: Chris Light, CC BY-SA 4.0, via Wikimedia Commons

The surprise was the point, and getting armour up there was the engineering feat. Maj Gen K. S. Thimayya is listed among the operation's commanders, with Brigadier Atal's brigade on the ground. It was then the highest altitude at which tanks had fought in combat anywhere, and the link-up at Kargil reopened the land route to Ladakh.

Panorama of Kargil town in Ladakh spread along a valley floor below dry brown mountains
Kargil town. The 24 November 1948 link-up here, after Operation Bison, reopened the land route to Ladakh.Photo: Saurabh Lall, CC BY 2.0, via Wikimedia Commons
Eighty years at one pass 194820122015201820202021-22Jan 20252024-25Jun 2026Feb 2028 Operation Bison: tanks retake the pass Z-Morh tunnel approved, ₹2,700 crore Z-Morh construction begins Zojila tunnel launched; Z-Morh stalls at 22% Z-Morh restarts under a new contractor BRO keeps the pass open: 73-day closure Sonamarg (Z-Morh) tunnel opens Closure down to 32 days Zojila main tunnel breaks through Completion target
Dates from the timeline table above; sources are the Wikipedia pages on Operation Bison and the Z-Morh tunnel, BRO figures via the press, and the July 2025 Lok Sabha reply.
DateEvent at Zoji La or on NH 1
1948Gilgit rebels and a Pakistani force seize Zoji La
1 Nov 1948Operation Bison: Indian tanks retake the pass
24 Nov 1948Link-up at Kargil reopens the route to Leh
Jul 2012Z-Morh (Sonamarg) tunnel approved at ₹2,700 crore; foundation stone Oct 2012
May 2015Construction of the Z-Morh tunnel begins
Jan 2018Zojila tunnel approved; foundation stone laid by PM Modi in May 2018
Jul 2018Z-Morh work stalls at about 22% after the developer's financial collapse
Jul 2020Z-Morh work restarts under a new contractor
Winter 2021-22BRO keeps the pass open to 4 Jan; closure only 73 days
Winter 2022-23Open to 6 Jan; closure 68 days
13 Jan 2025Sonamarg (Z-Morh) tunnel inaugurated
Winter 2024-25Closure 32 days; reopened about 1 Apr 2025
31 Jul 2025Lok Sabha told Zojila tunnel is 64% done, now due Feb 2028
15 Mar 2026Traffic resumes after a 6-day snow closure
9 Jun 2026Final breakthrough of the 13.15 km Zojila main tunnel

Why did the Srinagar-Leh highway close for half the year?

150 daystypical winter closure, BRO's figure
73 daysclosure in 2021-22
68 daysclosure in 2022-23
32 daysclosure in 2024-25

Because the pass collects deep snow and avalanches on both approaches, and for most of its history the only answer was to wait.

  • BRO's figure: a typical closure of about 150 days in earlier decades.
  • The Tribune's figure: 160 to 180 days.
  • The pattern: closed around October or November, reopened only in April or May.

During those months Ladakh depended on the Indian Air Force. A Tribune report from January 2026 notes that when both the Srinagar and Manali routes are shut, troops and supplies still rely on airlifts. For civilians in Kargil and Dras, winter meant months of stocked rations and expensive flights.

How did BRO shrink the Zoji La closure?

By clearing snow through the winter instead of waiting for spring, with more machines, better avalanche control and a policy decision to keep the pass open as long as possible.

  • Winter 2021-22: BRO kept Zoji La open until 4 January for the first time on record, and the closure lasted 73 days.
  • Winter 2022-23: 68 days, with the road open until 6 January and about 13,500 vehicles crossing between November and 6 January.
  • 2025: 32 days: 17 days of snowfall from 27 February to 16 March, then 14 days of clearance.
Zoji La winter closure, days
See the data as a table
Days closed (days)
Earlier average150
Winter 2021-2273
Winter 2022-2368
Winter 2024-2532

Source: BRO via Aviation Defence Universe (2022); The Tribune (Mar 2023, Apr 2025) · The earlier average is the BRO figure of about 150 days; The Tribune cites 160 to 180 days for earlier decades. Winter 2023-24 data was not found in the sources I opened.

A yellow crawler bulldozer with a blade and canopy clearing deep snow from a mountain road at Shinku La in Zanskar
A BRO crawler dozer clearing snow at Shinku La in Zanskar, a different pass. This is the kind of machine, run through the winter, that cut Zoji La's closure.Photo: This Photo was taken by Timothy A. Gonsalves. Feel free to use my photos, but please mention me as the author. I would, CC BY-SA 4.0, via Wikimedia Commons

The work is done by BRO's Project Vijayak, raised in 2010 and based in Kargil, which now has over 1,400 km of roads and 80 bridges in its charge. In January 2026 the pass was still open in mid-winter thanks to lighter snowfall, with temperatures between minus 10 and minus 20 °C at the top. A shorter 6-day closure followed in March 2026.

What is the Z-Morh, or Sonamarg, tunnel?

The Sonamarg tunnel is a 6.5 km road tunnel at 2,637 m on NH 1 between Gagangir and Sonamarg, inaugurated by Prime Minister Narendra Modi on 13 January 2025. It replaced a Z-shaped stretch of road that was regularly buried by avalanches, so Sonamarg is now reachable from Srinagar in winter. It was the first half of the all-weather plan for Ladakh, and the second half is the Zojila tunnel.

It took 13 years from approval. The government approved it at ₹2,700 crore in July 2012, building began in May 2015, and work stopped in July 2018 at about 22% when the original developer, part of the IL&FS group, ran out of money. NHIDCL re-bid the balance work, Apco Infratech took over, work restarted in July 2020 and the tunnel broke through by the end of June 2021.

Sonamarg Tunnel: An Engineering Marvel Driving Connectivity, Tourism, Economic Development, and Environmental SustainabilityAli A., Javaid S. J. and Varshney D. · Acta Innovations · 2026

The authors surveyed 104 people between 29 July and 6 August 2026, about 60% of them local residents and 14% tourists, and combined the answers with official project and tourism data. On a five-point scale, respondents rated connectivity benefits slightly positive (mean 3.21, significantly above neutral), tourism benefits similar but less certain, and economic benefits close to neutral (3.11). Using government figures for the Sonamarg-Zojila corridor (49 km shortened to 43 km, benchmark speed raised from 30 to 70 km/h), they estimate a saving of about 37 minutes, or 62%. The limit: a small, non-random sample with no stated recruitment method, so read it as a first local reaction, not a measured impact.

Read the paper (free)
6.5 kmSonamarg tunnel, open since 13 Jan 2025
13 yearsfrom approval to opening
2,637 maltitude of the Sonamarg tunnel

When will the Zojila tunnel open?

The current target is February 2028. The Zojila tunnel is a 13.153 km main tunnel at about 11,578 ft between Baltal on the Kashmir side and Minamarg near Dras, with about 17 km of approach roads, an escape tunnel and three vertical ventilation shafts.

The final breakthrough came on 9 June 2026, when Road Transport Minister Nitin Gadkari triggered the last blast, with Lieutenant Governor Manoj Sinha and Chief Minister Omar Abdullah present. When finished it will be Asia's longest bi-directional road tunnel and cut the crossing from more than three hours to about 15 minutes.

13.153 kmZojila main tunnel, broke through 9 Jun 2026
64%complete in July 2025, per Lok Sabha
₹6,809 croreestimated cost
3 h to 15 mincrossing time the tunnel is meant to deliver
Two tunnels under one road Srinagar sideDras Sonamarg tunnel6.5 km, 2,637 m BaltalMinamarg Zoji La pass road3+ hours, closes in snow Zojila tunnel 13.153 km about 15 minutes, target Feb 2028 Not to scale; heights and lengths are labels, not drawn proportions.
The all-weather plan for NH 1 in one picture. Figures from the Lok Sabha reply of July 2025, News On AIR (June 2026) and the Z-Morh tunnel record.
Lok Sabha written reply on the Zojila tunnel projectMinistry of Road Transport and Highways (Nitin Gadkari) · Lok Sabha · 31 July 2025

The minister told Parliament the project, executed by NHIDCL, was 64% complete, with ₹3,934.42 crore spent out of an estimated ₹6,809 crore. The total length is 30.18 km: 13.153 km of tunnel and 17.03 km of approach road. The completion date had slipped from 29 September 2026 to February 2028, with the delay blamed on COVID-19, a terrorist attack at the Sonamarg tunnel project site and extreme weather. The project employed 1,141 people, 77% of them from Jammu and Kashmir. The limit: progress percentages in parliamentary replies are self-reported by the executing agency.

Read the report of the reply
TunnelLengthAltitudeCostStatus (Nov 2026)
Sonamarg (Z-Morh)6.5 km, plus 6.05 km approaches2,637 m₹2,700 crore approved 2012; ₹2,378 crore for re-bid balanceOpen since 13 Jan 2025
Zojila13.153 km, plus 17.03 km approachesabout 11,578 ft₹6,809 crore estimatedBroke through 9 Jun 2026; target Feb 2028
The Sind valley at Sonamarg in Kashmir in October, with pine forests, meadows and snow-dusted peaks
Sonamarg, the last town before Zoji La. Since the Sonamarg tunnel opened in January 2025, it can be reached from Srinagar in winter.Photo: Tony Gladvin George, CC BY 2.0, via Wikimedia Commons

What will the tunnels change for riders?

A bus rounding a bend on the narrow unpaved shelf road of Zoji La with a rock wall on one side and a sheer drop on the other
The old shelf road over Zoji La: one lane, a rock wall on one side and a drop on the other. This is the stretch the tunnels will take most traffic off.Photo: Yogeshgupta26 at English Wikipedia, Public domain, via Wikimedia Commons

For riders the Srinagar route will become the easy door into Ladakh. Today the pass decides your schedule: early in the season Zoji La is often open weeks before Baralacha La on the Manali side, which is why so many first-timers start from Srinagar. Once the Zojila tunnel opens, the Srinagar-Kargil-Leh road will no longer depend on the snow at Zoji La, the pass that has always closed first and opened last on this route.

The ride will lose something too. The muddy, one-lane shelf road over Zoji La, with its convoy timings and truck queues, is one of the classic Indian riding experiences. Like Rohtang after the Atal Tunnel, the old road may stay open in summer for those who want it.

If you are choosing your route now, my comparison of Ladakh via Manali or Srinagar lays out the trade-offs, and the history of the Manali-Leh highway covers the other gate.

For the bigger picture on tunnels, see India's longest road tunnels and how Himalayan tunnels are changing road trips. BRO, which keeps the pass open, has its own history here, and more routes are on the Ride Atlas.

Questions people ask

What is the height of Zoji La?

About 3,500 m. BRO and Indian newspapers quote 11,500 to 11,650 ft, and the Zojila tunnel itself sits at about 11,578 ft. Sources differ by a few dozen metres depending on where the summit point is taken.

Is Zoji La open in winter now?

Mostly. BRO now clears it through much of the winter. Closures fell to 73 days in 2021-22, 68 in 2022-23 and 32 in 2024-25, and in 2026 the pass was open in mid-January with only short closures after heavy snow.

When will the Zojila tunnel be completed?

The target given to Parliament in July 2025 is February 2028. The main tunnel broke through on 9 June 2026; lining, ventilation and approach roads remain.

Why were tanks used at Zoji La in 1948?

Because infantry attacks had failed and the defenders did not expect armour at that height. Engineers widened the mule track from Baltal so M5 Stuart tanks could climb, and the surprise carried the pass on 1 November 1948.

Is the Srinagar route better than Manali for a first Ladakh ride?

For acclimatisation, usually yes: the climb is more gradual and Zoji La is lower than the Manali-side passes. Early in the season it is also often the only route open, as riders on the Tripoto thread found in early June.

Sources

  1. Wikipedia: Zoji La (accessed 2026)
  2. Wikipedia: Operation Bison (1948) (accessed 2026)
  3. Wikipedia: Z-Morh (Sonamarg) Tunnel (accessed 2026)
  4. News On AIR: Zoji-La tunnel achieves final breakthrough (2026)
  5. Swarajya: Zojila tunnel likely by February 2028 (Lok Sabha reply) (2025)
  6. Ali A. et al.: Sonamarg Tunnel, Acta Innovations (2026)
  7. Aviation Defence Universe: Zoji La opens after disruption against average closure of 150 days (2022)
  8. The Tribune: Strategic Zoji La reopens for traffic in record 68 days (2023)
  9. The Tribune: Border Roads Organisation opens Zoji La pass after 32 days (2025)
  10. The Tribune: Zoji La pass defies winter closure (2026)
  11. News On AIR: Traffic resumes on Zoji La after 6-day snow closure (2026)
  12. Wikipedia: Border Roads Organisation (Project Vijayak) (accessed 2026)
Zoji LaSrinagar-Leh highwayNH 1Operation BisonZojila tunnelZ-Morh tunnelSonamargProject Vijayak
Sapta

Sapta (Saptarshi Sarkar) is a mechanical engineer turned marketer in Bengaluru and a solo touring rider. He writes the seven Saptaverse blogs. Work with him or read more of RoadHook Rides.