Zoji La is the pass at about 3,500 m (BRO and the press give 11,500 to 11,650 ft) that carries the Srinagar-Leh highway, NH 1, from the Kashmir Valley into Ladakh. India recaptured it with light tanks on 1 November 1948 in Operation Bison, and for decades it stayed shut for 150 to 180 days each winter. BRO cut that to 32 days by 2025, and the 13.15 km Zojila tunnel beneath it achieved its final breakthrough on 9 June 2026, with completion targeted for February 2028.
- 1 November 1948: Operation Bison retook Zoji La with M5 Stuart light tanks, then the highest armour had fought anywhere.
- 150 days was BRO's typical winter closure; it fell to 73 (2021-22), 68 (2022-23) and 32 days (2024-25).
- 13 January 2025: the 6.5 km Sonamarg (Z-Morh) tunnel opened, 13 years after approval.
- 13.153 km Zojila tunnel broke through on 9 June 2026; target February 2028, at ₹6,809 crore estimated.
- More than 3 hours to about 15 minutes: the crossing time the tunnel is meant to deliver.
No Himalayan pass in India has a denser history per kilometre. Zoji La is about 100 km from Srinagar and 15 km beyond Sonamarg, and it is the only road gate between Kashmir and the Dras and Suru valleys. This post lays out what happened here and when, why the pass closes, how BRO shrank the closure, and what the two tunnels on NH 1 mean for riders.
Where is Zoji La and why does it matter?
Zoji La sits on the Great Himalayan range between Ganderbal district in Jammu and Kashmir and Kargil district in Ladakh.
| West side | East side | |
|---|---|---|
| Valley | Sind valley, around Sonamarg | Dras valley, on to Kargil and the Indus |
| Character | Green and wet | Dry |
| Administration | Ganderbal district, J&K | Kargil district, Ladakh |
The pass is short and low by Ladakh standards, but it is the first ridge the western weather systems hit, which is why it gets so much snow. Satellite-based climate data for the pass record lows of about minus 44 °C in December and January.
Whoever holds Zoji La holds the overland route into Ladakh from the west.
That combination of heavy snow and steep, avalanche-prone slopes is why the pass shaped every chapter of the road's history.

What happened at Zoji La in 1948?
In 1948, during the first India-Pakistan war over Kashmir, Gilgit rebels and a Pakistani force under Major Muhammad Khan Jarral seized Zoji La, cutting Ladakh off from the Kashmir Valley.
The Indian Army had already failed once at the pass. Operation Duck, an attack by the 77th Parachute Brigade under Brigadier K. L. Atal, could not shift the raiders. For the second try, renamed Operation Bison by Lt Gen K. M. Cariappa, the army chose something nobody expected at that height: tanks.
The M5 Stuart light tanks of the 7th Light Cavalry were moved through Srinagar dismantled and winched across bridges, while two field companies of the Madras Sappers turned the mule track from Baltal over the pass to Gumri into a jeep track that could carry them. On 1 November 1948 the brigade attacked with armour, backed by two regiments of 25-pounders and a regiment of 3.7-inch guns, and forced the pass. On 24 November it linked up at Kargil with troops advancing from Leh. India lost 75 killed and 296 wounded.
Wikipedia: Operation Bison (1948), with its cited military histories
The surprise was the point, and getting armour up there was the engineering feat. Maj Gen K. S. Thimayya is listed among the operation's commanders, with Brigadier Atal's brigade on the ground. It was then the highest altitude at which tanks had fought in combat anywhere, and the link-up at Kargil reopened the land route to Ladakh.

| Date | Event at Zoji La or on NH 1 |
|---|---|
| 1948 | Gilgit rebels and a Pakistani force seize Zoji La |
| 1 Nov 1948 | Operation Bison: Indian tanks retake the pass |
| 24 Nov 1948 | Link-up at Kargil reopens the route to Leh |
| Jul 2012 | Z-Morh (Sonamarg) tunnel approved at ₹2,700 crore; foundation stone Oct 2012 |
| May 2015 | Construction of the Z-Morh tunnel begins |
| Jan 2018 | Zojila tunnel approved; foundation stone laid by PM Modi in May 2018 |
| Jul 2018 | Z-Morh work stalls at about 22% after the developer's financial collapse |
| Jul 2020 | Z-Morh work restarts under a new contractor |
| Winter 2021-22 | BRO keeps the pass open to 4 Jan; closure only 73 days |
| Winter 2022-23 | Open to 6 Jan; closure 68 days |
| 13 Jan 2025 | Sonamarg (Z-Morh) tunnel inaugurated |
| Winter 2024-25 | Closure 32 days; reopened about 1 Apr 2025 |
| 31 Jul 2025 | Lok Sabha told Zojila tunnel is 64% done, now due Feb 2028 |
| 15 Mar 2026 | Traffic resumes after a 6-day snow closure |
| 9 Jun 2026 | Final breakthrough of the 13.15 km Zojila main tunnel |
Why did the Srinagar-Leh highway close for half the year?
Because the pass collects deep snow and avalanches on both approaches, and for most of its history the only answer was to wait.
- BRO's figure: a typical closure of about 150 days in earlier decades.
- The Tribune's figure: 160 to 180 days.
- The pattern: closed around October or November, reopened only in April or May.
During those months Ladakh depended on the Indian Air Force. A Tribune report from January 2026 notes that when both the Srinagar and Manali routes are shut, troops and supplies still rely on airlifts. For civilians in Kargil and Dras, winter meant months of stocked rations and expensive flights.
How did BRO shrink the Zoji La closure?
By clearing snow through the winter instead of waiting for spring, with more machines, better avalanche control and a policy decision to keep the pass open as long as possible.
- Winter 2021-22: BRO kept Zoji La open until 4 January for the first time on record, and the closure lasted 73 days.
- Winter 2022-23: 68 days, with the road open until 6 January and about 13,500 vehicles crossing between November and 6 January.
- 2025: 32 days: 17 days of snowfall from 27 February to 16 March, then 14 days of clearance.
See the data as a table
| Days closed (days) | |
|---|---|
| Earlier average | 150 |
| Winter 2021-22 | 73 |
| Winter 2022-23 | 68 |
| Winter 2024-25 | 32 |
Source: BRO via Aviation Defence Universe (2022); The Tribune (Mar 2023, Apr 2025) · The earlier average is the BRO figure of about 150 days; The Tribune cites 160 to 180 days for earlier decades. Winter 2023-24 data was not found in the sources I opened.

The work is done by BRO's Project Vijayak, raised in 2010 and based in Kargil, which now has over 1,400 km of roads and 80 bridges in its charge. In January 2026 the pass was still open in mid-winter thanks to lighter snowfall, with temperatures between minus 10 and minus 20 °C at the top. A shorter 6-day closure followed in March 2026.

What is the Z-Morh, or Sonamarg, tunnel?
The Sonamarg tunnel is a 6.5 km road tunnel at 2,637 m on NH 1 between Gagangir and Sonamarg, inaugurated by Prime Minister Narendra Modi on 13 January 2025. It replaced a Z-shaped stretch of road that was regularly buried by avalanches, so Sonamarg is now reachable from Srinagar in winter. It was the first half of the all-weather plan for Ladakh, and the second half is the Zojila tunnel.

It took 13 years from approval. The government approved it at ₹2,700 crore in July 2012, building began in May 2015, and work stopped in July 2018 at about 22% when the original developer, part of the IL&FS group, ran out of money. NHIDCL re-bid the balance work, Apco Infratech took over, work restarted in July 2020 and the tunnel broke through by the end of June 2021.
The authors surveyed 104 people between 29 July and 6 August 2026, about 60% of them local residents and 14% tourists, and combined the answers with official project and tourism data. On a five-point scale, respondents rated connectivity benefits slightly positive (mean 3.21, significantly above neutral), tourism benefits similar but less certain, and economic benefits close to neutral (3.11). Using government figures for the Sonamarg-Zojila corridor (49 km shortened to 43 km, benchmark speed raised from 30 to 70 km/h), they estimate a saving of about 37 minutes, or 62%. The limit: a small, non-random sample with no stated recruitment method, so read it as a first local reaction, not a measured impact.
Read the paper (free)When will the Zojila tunnel open?
The current target is February 2028. The Zojila tunnel is a 13.153 km main tunnel at about 11,578 ft between Baltal on the Kashmir side and Minamarg near Dras, with about 17 km of approach roads, an escape tunnel and three vertical ventilation shafts.
The final breakthrough came on 9 June 2026, when Road Transport Minister Nitin Gadkari triggered the last blast, with Lieutenant Governor Manoj Sinha and Chief Minister Omar Abdullah present. When finished it will be Asia's longest bi-directional road tunnel and cut the crossing from more than three hours to about 15 minutes.
The minister told Parliament the project, executed by NHIDCL, was 64% complete, with ₹3,934.42 crore spent out of an estimated ₹6,809 crore. The total length is 30.18 km: 13.153 km of tunnel and 17.03 km of approach road. The completion date had slipped from 29 September 2026 to February 2028, with the delay blamed on COVID-19, a terrorist attack at the Sonamarg tunnel project site and extreme weather. The project employed 1,141 people, 77% of them from Jammu and Kashmir. The limit: progress percentages in parliamentary replies are self-reported by the executing agency.
Read the report of the reply| Tunnel | Length | Altitude | Cost | Status (Nov 2026) |
|---|---|---|---|---|
| Sonamarg (Z-Morh) | 6.5 km, plus 6.05 km approaches | 2,637 m | ₹2,700 crore approved 2012; ₹2,378 crore for re-bid balance | Open since 13 Jan 2025 |
| Zojila | 13.153 km, plus 17.03 km approaches | about 11,578 ft | ₹6,809 crore estimated | Broke through 9 Jun 2026; target Feb 2028 |

What will the tunnels change for riders?

For riders the Srinagar route will become the easy door into Ladakh. Today the pass decides your schedule: early in the season Zoji La is often open weeks before Baralacha La on the Manali side, which is why so many first-timers start from Srinagar. Once the Zojila tunnel opens, the Srinagar-Kargil-Leh road will no longer depend on the snow at Zoji La, the pass that has always closed first and opened last on this route.
The ride will lose something too. The muddy, one-lane shelf road over Zoji La, with its convoy timings and truck queues, is one of the classic Indian riding experiences. Like Rohtang after the Atal Tunnel, the old road may stay open in summer for those who want it.
If you are choosing your route now, my comparison of Ladakh via Manali or Srinagar lays out the trade-offs, and the history of the Manali-Leh highway covers the other gate.
For the bigger picture on tunnels, see India's longest road tunnels and how Himalayan tunnels are changing road trips. BRO, which keeps the pass open, has its own history here, and more routes are on the Ride Atlas.
What's new
- Zojila tunnel achieves its final breakthrough, completion targeted for February 2028 News On AIR, Jun 2026
- Traffic resumes on Zoji La after a six-day snow closure News On AIR, Mar 2026
- BRO's Project Vijayak keeps Zoji La open in mid-January The Tribune, Jan 2026
- Zoji La reopens after a closure of only 32 days The Tribune, Apr 2025
Questions people ask
What is the height of Zoji La?
About 3,500 m. BRO and Indian newspapers quote 11,500 to 11,650 ft, and the Zojila tunnel itself sits at about 11,578 ft. Sources differ by a few dozen metres depending on where the summit point is taken.
Is Zoji La open in winter now?
Mostly. BRO now clears it through much of the winter. Closures fell to 73 days in 2021-22, 68 in 2022-23 and 32 in 2024-25, and in 2026 the pass was open in mid-January with only short closures after heavy snow.
When will the Zojila tunnel be completed?
The target given to Parliament in July 2025 is February 2028. The main tunnel broke through on 9 June 2026; lining, ventilation and approach roads remain.
Why were tanks used at Zoji La in 1948?
Because infantry attacks had failed and the defenders did not expect armour at that height. Engineers widened the mule track from Baltal so M5 Stuart tanks could climb, and the surprise carried the pass on 1 November 1948.
Is the Srinagar route better than Manali for a first Ladakh ride?
For acclimatisation, usually yes: the climb is more gradual and Zoji La is lower than the Manali-side passes. Early in the season it is also often the only route open, as riders on the Tripoto thread found in early June.
Sources
- Wikipedia: Zoji La (accessed 2026)
- Wikipedia: Operation Bison (1948) (accessed 2026)
- Wikipedia: Z-Morh (Sonamarg) Tunnel (accessed 2026)
- News On AIR: Zoji-La tunnel achieves final breakthrough (2026)
- Swarajya: Zojila tunnel likely by February 2028 (Lok Sabha reply) (2025)
- Ali A. et al.: Sonamarg Tunnel, Acta Innovations (2026)
- Aviation Defence Universe: Zoji La opens after disruption against average closure of 150 days (2022)
- The Tribune: Strategic Zoji La reopens for traffic in record 68 days (2023)
- The Tribune: Border Roads Organisation opens Zoji La pass after 32 days (2025)
- The Tribune: Zoji La pass defies winter closure (2026)
- News On AIR: Traffic resumes on Zoji La after 6-day snow closure (2026)
- Wikipedia: Border Roads Organisation (Project Vijayak) (accessed 2026)