How the Konkan Railway was built through the Western Ghats coast

For a century, engineers said a railway along the Konkan coast could not be built. A company owned by the Railways and four states did it in the 1990s, with 91 tunnels, nearly 1,900 bridges and soil that turned to slurry in the rain.

A railway tunnel on the Konkan Railway near Byndoor, Karnataka
Photo: Vaikoovery, CC BY 3.0, via Wikimedia Commons

The Konkan Railway was built in the 1990s by Konkan Railway Corporation Ltd (KRCL), a company incorporated on 19 July 1990 and owned by the Ministry of Railways (51%) and the states of Maharashtra, Karnataka, Goa and Kerala. Led by E. Sreedharan, it cut about 739 km of line from Roha to Thokur near Mangaluru through 91 tunnels and 1,891 bridges, and the complete line opened on 26 January 1998. It shortened the rail journey from Mumbai to Mangaluru from 2,041 km to 914 km.

Key takeaways
  • KRCL, incorporated on 19 July 1990, was 51% owned by the Railways and 49% by four states.
  • 738.9 km of line, with 91 tunnels (about 84.5 km) and 1,891 bridges, held to a 1 in 150 gradient.
  • Construction killed 74 people; 19 of those deaths were in the soft-soil tunnels.
  • The full line opened on 26 January 1998, at a cost of ₹3,555 crore.
  • Mumbai to Mangaluru by rail fell from 2,041 km to 914 km, and about 41 hours to 15.

The Konkan coast is a narrow strip between the Arabian Sea and the steep scarp of the Western Ghats, cut every few kilometres by rivers flowing west. Roads wound through it slowly, and for most of the 20th century trains from Mumbai to Goa or Mangaluru had to go inland, over the Ghats and round. This is the story of how the gap was closed: the money, the engineering, the monsoon, and the cost in lives.

738.9 kmroute length, Roha to Thokur (KRCL)
91tunnels, the longest 6.5 km at Karbude
₹3,555 croretotal project cost (KRCL)
26 Jan 1998full line from Roha to Mangaluru opened

Why was a Konkan coast railway considered so difficult?

The Konkan was hard because the line had to beat three things at once:

  • Rivers: dozens of west-flowing rivers cut across the route;
  • Hills: the spurs of the Ghats run down almost to the sea;
  • Soil: laterite and soft soil that becomes unstable in one of India's heaviest monsoons, most of it falling between June and October.

Any cutting or tunnel had to survive that water, and one tunnel near the Goa border showed what that meant.

The story

The Pernem tunnel, 1,561 m long on the Maharashtra–Goa border, was one of five soft-soil tunnels on the line. Work began in mid-1992. Under a crust of hard laterite lay lithomargic clay, and in the rains it flowed: mud ran into the bore, the roof caved, cavities opened and supports were squeezed. Chief Engineer (Tunnel) Vinod Kumar described strata that kept changing, from soft schist to hard laterite to soft clay, with water seeping in all the time.

On 26 August 1997 the tunnel collapsed, but engineer V. Jayasankaran had warned in time and the workers got out. On 10 October 1997 a bigger fall trapped executive engineer Ravi Kapoor, then 30, chest-deep in soil with his helmet crushed and a boulder on his foot. Jayasankaran stayed behind to free him, and he survived. The crews pushed on with fore-poling, drainage pipes and grouting and finished the bore on 10 January 1998. Sixteen days later the last section, Sawantwadi to Pernem, opened to traffic.

RailPost: The mercurial Pernem tunnel, a soft-soil hurdle for Konkan Railway engineers (Raghavendra Rao, 2020)

A plan that waited twenty years

The idea is old. Surveys for a coastal line were done from 1970 to 1972, and a short first piece, Apta to Roha, appeared in the Railway budget of 1978-79. A Lok Sabha debate in 1980 recorded cost estimates for the full Apta to Mangaluru route. But the Railways' budget never stretched to a project of this size. The line was built only when someone changed the way it was paid for.

Nivasar railway station on the Konkan Railway in Ratnagiri district, Maharashtra
Nivasar station in Ratnagiri district, Maharashtra. The line runs through a narrow belt of hills and river valleys between the Ghats and the sea.Photo: Unnikannan7, CC BY-SA 4.0, via Wikimedia Commons

Who built the Konkan Railway?

The Konkan Railway was built by KRCL, a special-purpose company set up under railway minister George Fernandes and headed by E. Sreedharan, the engineer later known for the Delhi Metro. KRCL was incorporated on 19 July 1990 under an agreement between the Ministry of Railways and the four states the line would serve.

ShareholderShare of equity
Ministry of Railways, Government of India51%
Maharashtra22%
Karnataka15%
Goa6%
Kerala6%

The structure mattered. As a company with its own board and its own funding, rather than a line item in the Railways' annual budget, KRCL could move quickly. Land acquisition for the whole route, involving about 43,000 landowners, was completed in roughly a year, and about ₹103 crore in compensation was paid to some 39,000 people, according to KRCL records cited on Wikipedia.

Sweden was the one foreign government that helped directly. A Sida evaluation by Karlis Goppers records a concessional credit of SEK 45 million that financed tunnelling equipment, including nine hydraulic drilling rigs and seven electro-hydraulic loaders.

Swedish Contribution to the Konkan Railway Construction Project in IndiaKarlis Goppers · Sida Evaluation 97/25 · Swedish International Development Cooperation Agency

This official evaluation reviewed Sweden's support to the project, which it described as one of the largest railway undertakings of its time. The evaluator visited KRCL's headquarters in Bombay and construction sites along the line and assessed the results against planned targets with a logical framework. The Swedish credit of SEK 45 million paid for nine hydraulic drilling machines and seven electro-hydraulic loaders for the hard-rock tunnels, out of roughly 84 km of tunnelling on the project. The limit: it evaluates one donor's equipment credit, not the whole project, and it was written while the line was still being completed, so it says little about later operations.

Read the evaluation (free)

How big was the engineering job?

The Konkan Railway needed 91 tunnels totalling about 84.5 km, 190 major and 1,701 minor bridges, and more than 220 km of cuttings to keep a gentle gradient of 1 in 150 along a hilly coast. Those numbers, from KRCL's own salient-features sheet, mean that more than a tenth of the route is underground and a large share of the rest is in cutting or on bridges.

groundrail at 1 in 150 tunneltunnel bridge over a river valley bridge cuttingembankment KRCL: 91 tunnels (84.5 km), 1,891 bridges, 220+ km of cuttings; deepest cut 50 m, highest bank 25 m
Why the numbers are so large: a line held to a gradient of 1 in 150 cannot follow the ground, so it tunnels through every spur and bridges every valley. Schematic, not to scale; figures from KRCL's salient features.
FeatureFigure
Route length (Roha to Thokur)738.941 km, broad gauge
Stations72
Tunnels91, total about 84.5 km
Longest tunnelKarbude, near Ratnagiri, 6.5 km
Major / minor bridges190 / 1,701
Longest bridgeSharavati river, Honnavar, 2,065.8 m
Panval Nadi viaduct, Ratnagiri420 m long, 64 m listed by KRCL; India's first bridge built by incremental launching
Longest steel span124.2 m, over the Zuari and Mandovi rivers in Goa
Deepest cutting / highest embankment50 m / 25 m
Ruling gradient1 in 150 (0.67%)
Project cost₹3,555 crore

The Panval Nadi viaduct near Ratnagiri is the best-known structure. KRCL describes it as the first bridge in India built by incremental launching: the prestressed concrete box girder was cast in segments on land and pushed out across the piers, instead of being assembled on scaffolding in the valley. For a deep valley in monsoon country, that meant far less work in the air and in the river.

The railway at Kumta, a Konkan Railway station in Uttara Kannada, Karnataka
The line at Kumta in coastal Karnataka. Long stretches of the route sit in cuttings or on embankments to hold the 1 in 150 gradient.Photo: Unnikannan7, CC BY-SA 4.0, via Wikimedia Commons

Why were the tunnels the hardest part?

Hard rock was the easy case. The hard tunnels were in soft, water-soaked soil that flowed into the bore.The lesson of the Konkan tunnels

Construction killed 74 people in all, and 19 of those deaths happened in the soft-soil tunnels, which took about four years of work, according to a tunnelling association newsletter cited on Wikipedia. The Pernem tunnel in the story above took about six years and was completed only in January 1998, weeks before the line opened end to end.

hard laterite crust soft lithomargic clay, water-bearing tunnel bore fore-poles over the crown seepageseepage perforated drain pipes grout injectedto bind the clay
Why the soft-soil tunnels took years. Clay under the laterite turned to mud in the monsoon, so crews drove fore-poles ahead of the face, drained water through perforated pipes and grouted the ground. Schematic based on the RailPost account of the Pernem tunnel.

Hard-rock tunnels were a different job.

The Karbude tunnel near Ratnagiri, at about 6.5 km, is the longest on the line. Hard-rock tunnels like these were driven with drilling rigs and loaders of the kind Sweden financed. Six of the line's tunnels have ballastless track, KRCL says.

What did the monsoon do to the line?

The monsoon is the Konkan Railway's permanent enemy. In 1998, the first season after opening, landslides and boulder falls were widespread, and slips have recurred every year. Two of the worst accidents on the line came from monsoon slips: at Vaibhavwadi on 22 June 2003, when 51 people died, and at Karanjadi on 16 June 2004, when 20 died.

How the line fights back

KRCL's answer has been decades of geotechnical work:

  • flattening cut slopes;
  • soil nailing, rock bolting and shotcrete;
  • gabion walls and micropiles;
  • boulder nets and lined drains.

Every year the line runs a separate monsoon timetable. In 2026 it ran from 15 June to 20 October, with:

  • speed restrictions;
  • 657 trained staff patrolling vulnerable stretches round the clock;
  • rain gauges at nine stations and flood warning systems at four bridges;
  • a rule to stop trains if water rises more than 100 mm above rail level.
View from a Konkan Railway train during the monsoon
The Konkan line seen from a train in the monsoon. The same rain that makes the coast green loosens the cuttings above the track.Photo: Vinayaraj, CC BY-SA 3.0, via Wikimedia Commons
Stabilisation of Deep Soil Cut Using Micropiles and Soil NailingV.V. Vaishampayan and S.P. Bhosle · 7th International Conference on Case Histories in Geotechnical Engineering, Chicago · 2013

This case history describes one failed cutting on the Konkan Railway at chainage 344/900 km, in lateritic soil. The cut was about 100 m long and the hillside rose about 20 m above track level. A gabion wall had been built, but heavy monsoon rain in June 2000 caused the slope to collapse, pushing the wall sideways and shifting the nearby track. The fix, built between January and May 2001, combined soil nails and micropiles with the existing gabion wall, and load tests on the nails and piles checked the design. The authors report the slope stayed stable for the following ten years. The limit: it is a single-site report by the contractor's engineers, not a survey of the whole line.

Read the paper (free)

What did the Konkan Railway change?

The Konkan Railway cut the rail distance between Mumbai and Mangaluru from 2,041 km to 914 km and the journey from about 41 hours to 15, by KRCL's figures. Goa got a direct broad-gauge link to Mumbai and to Kerala, and coastal towns like Ratnagiri, Kudal, Karwar, Kumta and Udupi got through trains for the first time.

Rail distance with and without the Konkan Railway
See the data as a table
Via older route (km)Via Konkan Railway (km)
Mangaluru–Mumbai2041914
Mangaluru–Ahmedabad26531358
Mangaluru–Delhi30332249
Kochi–Mumbai18491336

Source: Konkan Railway Corporation, salient features

Trucks on trains

The line also invented a new kind of freight in India. From 1999 KRCL ran Roll-on Roll-off (RoRo) trains, which carry loaded lorries on flat wagons, first between Kolad and Verna and from 2004 to Surathkal. The trucks skip a long stretch of hilly coastal road, and the highway is spared their weight. By 2009 the service had carried about 1.6 million trucks, according to figures cited on Wikipedia.

The first passenger section, Udupi to Mangaluru, opened on 20 March 1993, sections opened in stages, and the whole Roha to Mangaluru line opened on 26 January 1998, with the Matsyagandha Express starting from 1 May 1998. Electrification of the route, begun with a foundation stone in November 2015, was completed in March 2022. The line is broad gauge throughout; if you want to know why that matters, read why Indian Railways uses broad gauge, and for the longer story, Indian Railways from 1853.

Surathkal railway station near Mangaluru, Karnataka
Surathkal near Mangaluru, the southern end of the Roll-on Roll-off truck service since 2004.Photo: Sujithshivam511, CC BY-SA 4.0, via Wikimedia Commons

Is the Konkan Railway merging with Indian Railways?

Yes, the merger has been agreed in principle. By May 2025, all four shareholder states had consented to merging KRCL into Indian Railways, Maharashtra last, on two conditions: that the Railways repay the state its contribution of about ₹394 crore, and that the name "Konkan Railway" be kept. The reason is money. As a separate company, KRCL has struggled to fund doubling, new stations and safety works from its own revenue, while Indian Railways can draw on the Union budget. The Railway Board was to work out the details.

The Konkan line also matters to anyone who travels the coast by road. The parallel highway and the railway share the same rivers and hills, and the ride blog's Konkan coastal highway guide covers the road side of this geography. For long rail journeys that use the line, see India's longest train routes.

Questions people ask

Who built the Konkan Railway?

Konkan Railway Corporation Ltd, a company owned 51% by the Ministry of Railways and the rest by Maharashtra, Karnataka, Goa and Kerala. E. Sreedharan led it as chairman and managing director during construction.

Why was the Konkan Railway so difficult to build?

The route crosses many rivers and the spurs of the Western Ghats through soft, water-soaked soil in a very heavy monsoon. It needed 91 tunnels, nearly 1,900 bridges and deep cuttings, and soft-soil tunnels caused repeated collapses. Construction cost 74 lives.

When did the Konkan Railway open?

The first section, Udupi to Mangaluru, opened on 20 March 1993. The full Roha to Mangaluru line opened on 26 January 1998, and through passenger services between Mumbai and Mangaluru started in May 1998.

Which is the longest tunnel on the Konkan Railway?

The Karbude tunnel near Ratnagiri, about 6.5 km long, according to KRCL.

What is RoRo on the Konkan Railway?

Roll-on Roll-off: loaded trucks are driven onto flat wagons and carried by train along the coast, then driven off. KRCL started it in 1999 between Kolad and Verna.

Sources

  1. Konkan Railway Corporation: Salient features. Source for route length, stations, tunnels, bridges, cuttings, gradient, cost, Panval viaduct and distance and time savings.
  2. Konkan Railway Corporation: RTI details. Source for the 19 July 1990 incorporation.
  3. Konkan Railway: Monsoon preparedness 2026 (2026)
  4. Wikipedia: Konkan Railway, citing KRCL documents, the ITA tunnelling newsletter, The Hindu and Lok Sabha debates. Source for land acquisition, construction deaths, opening dates, accidents, RoRo and electrification.
  5. Goppers K.: Swedish Contribution to the Konkan Railway Construction Project in India, Sida Evaluation 97/25
  6. Vaishampayan V.V. and Bhosle S.P.: Stabilisation of Deep Soil Cut Using Micropiles and Soil Nailing, 7th ICCHGE (2013)
  7. Free Press Journal: Konkan Railway set to merge with Indian Railways (2025). Source for shareholding and merger conditions.
  8. Deccan Chronicle: Konkan Railway deploys AI system to detect landslides (2026)
  9. RailPost: The mercurial Pernem tunnel, a soft-soil hurdle for Konkan Railway engineers (2020; source for the Pernem tunnel story, its geology and construction methods)
Konkan RailwayKRCLE. SreedharanKarbude tunnelPanval Nadi viaductSharavati bridgeRoRoWestern Ghatsmonsoon landslides